Brindishe Green Primary School

Lewisham

This project comprised of three distinct work faces, which ran concurrently during the six-week school summer holiday period, programme assurance being essential to all sections of this project for the school return on September.

The first phase of works involved the reconfiguration of an existing nursery building to provide a new ‘bulge class’. This included the formation of a number of new classrooms, a toilet block, and staff kitchen.  Alterations to the existing building were extensive with new openings formed and the replacement of all existing windows. Works also encompassed mechanical and electrical installation, flooring finishes and data wiring.

Phase two of our delivery involved the refurbishment of the school’s existing pupil toilets, including new flooring, cubicles, sanitaryware and a full building services installation.

The third and final phase required the removal of existing raised timber decking and replacement with new block paved hard-standing areas, raised platforms, and staircases.  Additionally, we undertook repairs to the boundary wall and undertook the cleaning of the existing canopies.

Lets work together